Operational Readiness Reviews for the HB-Line at the Savannah River Site

Number
1992-3
Status
Closed

Documentation

Timeline (1992 - 1994)

1994
February 1, 1994
Closed
1992
November 30, 1992
DOE Implementation Plan Due
November 16, 1992
Public Comment on DOE Response Due
October 16, 1992
DOE Response Printed in Federal Register
September 21, 1992
DOE Implementation Plan Received
DOE Response Received
September 3, 1992
DOE Response Due
July 6, 1992
Public Comment Due
June 4, 1992
Recommendation Printed in Federal Register
May 29, 1992
Recommendation Delivered to DOE