DOE's Facility Representative Program at Defense Nuclear Facilities

Number
1992-2
Status
Closed

Documentation

Timeline (1992 - 1999)

1999
1996
October 1, 1996
Closed
1995
1993
January 15, 1993
DOE Implementation Plan Approval
1992
October 29, 1992
DOE Implementation Plan Due
August 31, 1992
Public Comment on DOE Response Due
July 31, 1992
DOE Response Printed in Federal Register
July 21, 1992
DOE Response Received
July 20, 1992
DOE Response Due
July 6, 1992
Public Comment Due
June 4, 1992
Recommendation Printed in Federal Register
May 28, 1992
Recommendation Delivered to DOE