Restart of the K, L, and P Reactors at Savannah River Site

Number
1990-1
Status
Closed

Documentation

Timeline (1990 - 1992)

1992
1991
1990
November 28, 1990
DOE Implementation Plan Approval
July 13, 1990
DOE Implementation Plan Received
July 12, 1990
DOE Implementation Plan Due
May 14, 1990
Public Comment on DOE Response Due
April 15, 1990
DOE Response Due
April 13, 1990
DOE Response Printed in Federal Register
April 10, 1990
DOE Response Received
March 31, 1990
Public Comment Due
March 1, 1990
Recommendation Printed in Federal Register
February 22, 1990
Recommendation Delivered to DOE