Prioritization for Stabilizing Nuclear Materials

Number
2000-1
DNFSB Staff Contact
David Gutowski
Status
Closed
DOE Issue Lead
Steven Petras
DOE Responsible Manager
James Owendoff

Documentation

Timeline (2000 - 2013)

2013
2012
2010
2009
2008
2007
2006
January 5, 2006
DOE Implementation Plan Approval
2005
December 1, 2005
DOE Implementation Plan Received
2004
2003
2002
2001
2000
June 26, 2000
DOE Implementation Plan Due
April 26, 2000
Public Comment on DOE Response Due
March 27, 2000
DOE Response Printed in Federal Register
March 16, 2000
DOE Response Due
March 14, 2000
DOE Response Received
February 25, 2000
Public Comment Due
January 26, 2000
Recommendation Printed in Federal Register
January 14, 2000
Recommendation Delivered to DOE